When is a building permit required?
- Construction of any building or other structure with a total construction cost in excess of $100.00.
- Construction of an addition to any building or structure.
- Demolition of a building or structure.
- A change in the occupancy of a building that effects fire egress and exit requirements or other occupancy restrictions.
- The installation or alteration of any equipment regulated by this code.
- Any change to a roof line, e.g. from a flat roof to a gabled or hip roof also normal shingle replacement.
Electrical permits, plumbing permits and mechanical permits are considered separately.
A building permit is NOT required for any building maintenance, such as siding, painting, replacement of doors and windows in existing openings. UNLESS, it would cause a change in occupancy requirements or affect required fire egress and exits etc.
What is the procedure for Permit Application?
-
Fill out the Application for Building Permit and Plan Review, providing all information required for the project. For one and two family dwellings the applicant must also complete the One & Two Family Plan Review form.
- For structures to be constructed within a subdivision, the applicant should be aware of any restrictive covenants that may apply. Generally, covenants are recorded at the Office of the County Clerk.
- Any application submitted for the construction of a building or structure to be used by the public MUST include a set of plans for such on which an architect or structural engineer licensed by the State of Illinois to perform such work has signed and affixed his seal thereon.
- The site plan must indicate all set-back distances and dimensions (check for conformance with zoning regulations). All set-backs are measured from the property line and NOT from the curb or street center.
- A requirement for the issuance of a demolition permit is for the applicant to NOTIFY JULIE for a dig number. This will assure that utilities have been properly disconnected.