Commercial/Industrial/Public Building Demolition Requirements
- Completed Demo application B.
-
Have Mt Carmel Public Utility complete Demolition Sign off Form in Demo Application.
-
The application will not be approved without the completed form signed off by a Mt. Carmel Public Utility Representative.
-
- A surety bond in the amount of S5,000.00 or a cash bond in the amount of $500.00.(once cleanup and completion of demolition bond will be released).
- Evidence that arrangements have been made to properly collect and dispose of demolition material.
- Completion of demolition and cleanup within 60 days from start date.
- A permit fee of $100.00.
Illinois asbestos laws govern the proper executions of demolition on commercial properties, garages, homes, warehouses etc.